Painter’s Guide to Lean Workflow: Applying Little’s Law for Maximum Productivity

A Step-by-Step Guide to Increasing Job Throughput and Reducing Wasted Time

Torlando Hakes
40 min readFeb 20, 2024

--

Painting businesses, large and small, all wrestle with the same challenges: scheduling projects, ensuring timely completion, and managing customer expectations. While many factors play a role, at its core, painting is a queuing system subject to the universal principle of Little’s Law. Understanding this simple concept used for decades in manufacturing can bring powerful insights to streamline your workflow and boost profitability. It might even reveal the scariest truth of it all, that finding good people isn’t that hard, but becoming a good manager is. But it doesn’t have to be that way.

What is Little’s Law?

Little’s Law reveals the relationship between three fundamental factors in any work system:

  1. Throughput (L): The average number of production units (we’ll use points in this article) your business completes in a defined period, like an hour, day, or sprint (2-week period).
  2. Work-in-Progress (WIP): The average number of points your team has committed to within projects currently underway or in the sprint backlog.
  3. Cycle Time (W): The average time to complete a project, which is dependent on its total points.

The Little’s Law formula: L = WIP / W

Ex. If your team wins a small job that is bid at 102 points at a price of $40/pt, the total cost of labor is $4,080. You’ll assign a crew of three painters. Your lead painter can produce 16 points per day. Your middle painter can produce 10 points per day. Your new apprentice can produce 8 points per day. As a team, they produce 34 points per day. With this production rate, they will need 3 days to complete the project. Therefore, Little’s Law mathematically describes their throughput by dividing the total number of points in the project by the number of days given for it.

34 pts/day = 102 pts / 3 days

Understanding the expression helps us find the information required for when there are unknown variables. For example, if we wanted to know the cycle time of a job, or in other words, how long a job will take based on our crew’s capacity. We rearrange the formula as follows:

W=WIP/L or;

3 days = 102pts / 34pts/day

Making Sense of Little’s Law for Painters Using Points

The point system converts every unit of measurement in the house into a single unit, which makes the math easier to do in Little’s Law. Understanding the interaction of those three factors (L, WIP, W) is crucial to optimizing your operations.

Here’s what Little’s Law tells us:

  • Projects on Hold = Longer Customer Wait Times: Committing to too many points before the team can actually work on them leads to long “lead times” for new customers.
  • Completing Points Faster Matters: If you find ways to finish projects more quickly, you can complete more total points with the same workforce.
  • Team Composition Makes a Difference: Little’s Law is highly influenced by the individual efficiency of your painters. Remember, their speed dictates your potential throughput.
  • The Ideal Balance: Each team has a sweet spot — that right amount of points on the schedule for maximum output without leading to excessive project delays.

Individual Throughput: The Key to Applying Little’s Law Effectively

The Craftsman Painter point system helps track not just overall throughput, but the individual painter’s capabilities:

  • Know Your Painters: Individual throughput isn’t just about raw speed. Experience impacts task efficiency. A newer painter’s ability to complete 2 points/hour could be due to working on less intricate tasks, while an experienced painter reaches that same throughput rate but on more complex work.
  • Points Are Mostly Equal…Mostly: Some tasks won’t fit the ‘ideal’ timing per point, making accurate project estimation vital. If several complex tasks cluster in one project, total cycle time (and customer expectation setting) needs to be adjusted beyond simple point counting.
  • Task Allocation for Optimal Speed: Matching task complexity to painter skill creates better overall flow in the system.

“Batching” easier tasks lets new painters build speed; while experts tackle tricky areas of high-point projects. This requires flexible scheduling, as drying times within one project will determine when another can start — making process flow visualization a vital tool.

Remember: Points allow for a standardized unit of work, making Little’s Law calculations more meaningful in comparison to whole projects with wildly varying sizes.

Sample Scenario: Calculating Potential Team Throughput

Team Composition

  • Painter A (Craftsman): 2.5 points/hour
  • Painter B (Journeyman): 1.75 points/hour
  • Painter C (Apprentice): 1 point/hour

Assumptions

Sprint length: 2 weeks (80 working hours each painter) Tasks may exceed ‘points per hour’ estimates, depending on the painter’s skill level and the number of statistical fluctuations (that is delays that are predictably unpredictable).

Individual Ideal Throughput

  • Painter A: 2.5 points/hour * 80 hours = 200 points
  • Painter B: 1.75 points/hour * 80 hours = 140 points
  • Painter C: 1 point/hour * 80 hours = 80 points

Team’s Potential Sprint Throughput: In this scenario, the total number of points able to be produced by this team in one sprint is 420, which is the sum of each of their individual points.

Managing Expectations

With a less experienced team, greater variability occurs due to process flow inefficiencies. Process flow isn’t the individual performance of the team, it is the collective flow of work produced by the team. Analyze historical data to understand how close they get to the ‘ideal’. Perhaps this crew operates closer to 65–75% of calculated capacity as a general starting point. Aim for sprints initially in the region of 270–315 points to prevent overloaded schedules.

Skill Level Implications

  • Craftsman Level: (L=2.5 to 3 pts/hr) While the most capable in terms of speed and handling complexity, this throughput estimate may be ambitious and often missed due to time spent leading and mentoring others during the sprint, impacting total available work hours.
  • Journeyman Level: (L=1.75 to 2.25 pts/hr) Provides consistent speed, but less adaptable with very complex tasks; projects need cautious estimates if intricate work (likely beyond this painter’s comfort zone) is heavily present.
  • Apprentice Level: (L=1 to 2 pts/hr) Greatest variability is anticipated. Prioritize ‘batching’ simpler, repeatable tasks for efficiency gains as they improve, as opposed to dropping them immediately into multiphase projects.

Additional Considerations

Training Focus: Painter C has the highest potential growth area for your entire team’s throughput. Prioritize ‘point speed’ improvement alongside task complexity mastery for the long term.

Project Selection: A diverse ‘pool’ of projects (size and complexity) is strategic. Match workloads to painter strengths for balance, while still tracking total WIP.

“Buffering” Even More Crucial: Underestimates with this skill mix have higher impact (think: Craftsman ‘rescue efforts’ on Apprentice issues). Buffer zones per project could be necessary until a baseline consistency forms.

Key Takeaways

Little’s Law isn’t magic — It’s a tool! It shows you realistic lead times given present crew makeup, where improvements are most impactful, and how managing WIP appropriately avoids burnout.

Invest in Apprentice skill leveling — This yields the biggest throughput gain over time.

Plan sprints wisely: Be conservative at first, use historical data, and match tasks to skill levels for overall system flow.

Action Items: Applying Little’s Law Practically

Quantify Painter Throughput:

  1. Track Individual Performance: Record the total points each painter completes over several sprints or weeks. Divide this by their total working hours to obtain their average “points per hour.”
  2. Do the Math: Painter B completes 280 points in a month, working 160 hours, yielding an average throughput of 1.75 points/hour.
  3. Data is Key: This provides baselines and reveals individual strengths or areas for improvement.

Track Project and Task Duration:

  • Measure Project Length: Document the actual time it takes to complete projects of varying point sizes.
  • Analyze Outliers: Observe any tasks consistently taking longer than the 20–60 minute target per point. These are either estimation issues or skill areas needing focused training.
  • Refine Over Time: This data makes project estimates more accurate, directly impacting WIP management and customer expectations.

Analyze Your WIP Sweet Spot:

  • Spot Bottlenecks: Examine whether jobs routinely run past schedule. A too-high WIP might be overloading your crew relative to their current speed. Bottlenecks slow down WIP processing time and increase backlog.
  • Gauge Growth Potential: Conversely, frequent painter downtime waiting for projects could indicate your WIP is too low, and with current throughput, more work could be accepted without strain.
  • Continuous Learning: Use this data to adjust your sprint capacity, accept projects intelligently, and improve scheduling over time.

Important Considerations:

  • Variability: Expect a bit of fluctuation, especially with newer/training painters. Little’s Law works best with averages over time.
  • Communication: Be transparent with customers on how their “point heavy” projects with complex tasks influence lead times.
  • Process and Skill: Little’s Law reveals insights beyond raw speed. Drying/wait times could be your true problem — requiring different solutions than simply demanding everyone go faster.

What This Means For Painters

In simple terms, Little’s Law tells us:

More Work In Progress = Longer Wait Times: Too many projects in the pipeline slows completion and makes client lead times longer.

Think of those times clients call, and you find yourself quoting ‘4–6 weeks out’ just to start. That’s because your system is likely backlogged with a high WIP.

While busy is good, this also risks unhappy customers tired of waiting and may lead to you missing out on new leads from referrals if word spreads that you always run way behind.

Shorter Cycle Times = Higher Throughput: Streamlining processes to finish projects faster allows for more overall work in the same time frame.

What if the answer to getting more work done isn’t just adding people? What if the answer is management!

The goal of operations is to make money and eliminating bottlenecks means more money and less stress because it lets you either accept more customers or enjoy shorter, less frantic sprints (your choice).

Balancing The System = Maximum Efficiency: There’s a sweet spot for how much work to have ‘in progress’ for your unique circumstances.

This ‘Goldilocks zone’ isn’t about being either crazy busy or having painters idle. It’s where your crew has a steady flow, jobs come in at a perfect pace for your current throughput, and everyone feels they’re working to their best capacity without burnout. The challenge of keeping this balance is not easy with a seasonal business. But keeping a core team that you keep busy all year and having a network of collaborators for when things get busy is an option to keep flow going without the liability of carrying idle workers.

Little’s Law helps you uncover this balance through trial and error: “This month we tried x points per sprint, things kinda crashed in week 2… next time let’s reduce and see if flow gets smoother.”

Beyond The Fundamentals

Little’s Law isn’t just about scheduling, it impacts your entire business:

  • Pricing: A smoothly running system means faster, predictable job completion. With confidence, you might consider slightly higher pricing, reflecting your expertise in providing timely (yet quality) finishes. Increasing price
  • Hiring Decisions: Do you constantly feel pressure to add another painter? First, use Little’s Law data. Maybe instead of extra people, existing painters lack efficiency — then focused training for your crew has a higher ROI.
  • Customer Experience: This extends beyond simply “when can you start?”. Being upfront about how “point complexity” influences project length is part of the equation too — transparent clients become less likely to hassle you mid-project, which in itself speeds up work!

Practical Example: Sarah’s Painting Proves Little’s Law

Meet Sarah. She is an artist who found a niche in painting and runs a small team (herself, one skilled painter, and an apprentice). Here’s how Little’s Law impacted her business:

The Old Way: Sarah used to take on any job offered, excited by the volume of work. However, project delays became routine, leaving customers frustrated with constant changes to finish dates. Referrals started slowing down, as people grumbled about wait times even before work began.

Little’s Law Lightbulb: Sarah tracked her team’s actual ‘throughput’ (how many points were usually finished per sprint). Then, she looked at historical WIP — how many points were ‘active’ within a given cycle. Realization struck: the WIP load always far exceeded what they could actually handle!

Applying the Lesson: Instead of “all in” on every job, Sarah analyzed:

  • Average Cycle Time: How long ‘point-heavy’ vs typical jobs were taking
  • Bottlenecks: Those darn high-cut dry times between coats truly added up!
  • Individual Speed: Her apprentice was improving, but complex tasks slowed everyone down when assigned incorrectly.

Putting It Into Practice:

Sarah started taking fewer total point projects per sprint, balancing it with smaller ‘filler’ jobs in between drying phases of the biggies.

She invested in fast-dry solutions when it made sense cost-wise.

Task assignment evolved; the apprentice got ‘batched’ simpler work on large projects, while more experienced painters tackled tricky high-point areas for maximum overall time saved.

The Result:

Jobs moved through the system faster. Less ‘waiting on things to dry’ time made everything more efficient. Clients, kept updated with more realistic estimates from the start, were far happier with timelines being met! Fewer mid-project delays improved overall team morale. Sarah had time to improve their pricing structure a bit, since less frantic = better work.

Amazingly, that first month after using Little’s Law thinking, their completed paint point total was slightly HIGHER because smooth progress beat raw frenzy every time.

Disclosure: This is a simplified example. External factors beyond scheduling (weather, illness, sudden client changes, etc.) still exist. But Little’s Law gives you a more powerful data-informed tool to handle them as part of your normal operation.

Sarah’s Painting: Before and After Little’s Law

Before

  • Average Sprint Throughput: Let’s say her ‘old’ method usually averaged around 300 points reliably completed per sprint while juggling tasks haphazardly.
  • Average WIP: Historically, she carried roughly 450–500 points of unfinished work with varying degrees of progress per sprint.
  • Customer Experience: Projects stretched into 3 & 4-week affairs weren’t uncommon, leaving both clients and the team stressed as delays cascaded from job to job.

After Applying Little’s Law

Strategic Sprint Planning: Analyzing past sprints and task bottlenecks, Sarah reduced ‘accepted’ point loads into the 350–380 range for a start.

Cycle Time Focus:

Fast-dry products for base coats and strategically letting coats dry during lunch breaks and overnight shaved off about 8–10 ‘wait’ hours across several average-sized projects.

Optimized task assignment (apprentice on ‘batch’ jobs, experts on complex ones) shaved another 5–8 hours in total across larger projects.

WIP Management: Sarah became strict; If total active points hit 400, new lead times got longer — no overloading regardless of how tempting the project!

The Impact

Cycle Time Shortens: Through the combination of changes, average projects finished up about 10–15% faster than before.

Throughput Increase: While Sarah did slightly fewer points at the very start, it quickly became apparent that her new capacity was roughly 350–370 points reliably per sprint — about a 15% gain!

Morale Improves: Less project pileup stress made every workday seem smoother, improving quality and minimizing silly rework mistakes that added FURTHER delays previously.

Key Takeaway: The increase wasn’t from working longer hours or hiring more people. Little’s Law helped Sarah find efficiencies she didn’t realize were hidden within her existing operation and adjust sprint loads to match that real-world capacity.

Additional Note: Further refinement is always possible! Once the baseline is established, perhaps the apprentice keeps improving, letting Sarah then handle 400+ points comfortably without overload down the line. This is why tracking is vital alongside these principles.

Key Questions Inspired by Sarah’s Experience

“Where’s My True Capacity?”

Can I honestly say how many points my team finishes, on average, within a set timeframe? Do I just go by a ‘feeling’ of what we can handle?

Do I actually track how many points are in some stage of progress at any given point in time? (The difference between this and my ideal throughput will point towards problems to tackle.)

“What’s Really Slowing Us Down?”

Beyond blaming painter speed, where do ‘dead hours’ happen within a project? How long does drying actually take on various jobs, versus active work done?

Am I matching tasks to skill well? Could putting complex bits on my backlog hurt overall progress, even if individually the work quality is great?

“Am I Communicating Honestly?”

Are my lead times based on what customers want to hear, or what my crew honestly delivers?

Can I be upfront when a big project has lots of intricate elements?

“Could Fewer Projects = More Success?”

Would I make more profit completing fewer projects but done faster (allowing for slightly improved pricing) without increasing my workforce size? How many ‘extra’ jobs is a happy, less-stressed crew worth to me as the owner? (Little’s Law can make burnout less frequent!).

Practical Applications: How Painters Use Little’s Law

Understanding Your Capacity: Turning Measurements into Manageable Units

In the Craftsman Painter system, we don’t track job progress solely by square footage, linear feet, or other raw measurements. Instead, we break things down into points. Why?

The Points Premise: A point ideally equates to roughly 20–60 minutes of active work. Knowing a job is ‘120 points’ lets you visualize how many estimated labor hours exist, but without being tied to one painter’s specific speed.

Beyond Surface Area: A tiny room with complex trim may take longer than a big, empty box to paint. Points let you account for task complexity, ensuring fair job estimates and achievable sprint schedules.

Tracking by Skill: Individual point throughput becomes meaningful. Over time, an Apprentice completing more points within a sprint reflects growth, improving your overall team capacity.

Calculating Points: Turning Spaces into Workloads

We have simple rules for translating those standard job measurements into point totals:

Our process uses a Fibonacci-inspired rule for easy tracking. Here’s a crash course on the rule:

  • The first two numbers are 0 and 1.
  • To get the next number, add the previous two together.
  • Example
  • 0, 1, 1, 2, 3, 5, 8, 13, 21, 34…
  • 0 + 1 = 1
  • 1 + 1 = 2
  • 1 + 2 = 3
  • 2 + 3 = 5 …and so on

Wall Base Point Calculation: Divide a room’s total perimeter by 4. This is your starting point for wall work.

Ceiling & Trim Complexity: Points for these elements stem from that base wall calculation. Ceilings are two steps ‘down’ in complexity from the wall calculation. Trim items are three steps ‘down’ from the base wall point count.

Simplified Standards: Doors, windows, standard frames, each get roughly 1 point for consistency.

Repairs: Repairs range from 1 to 3 points (or occasionally more for massive fixes). Experienced judgment is vital — both severity and location (like high ceilings vs. easy reach) impact estimated work time.

Skill Level: Turning Points Into Real Time

Think of points like little segments of work. We’re striving to quantify an amount of work of a specific task to an equal amount of work compared to other tasks. How much wall space is the equivalent to an amount of trim? How much ceiling space is equivalent to painting a door? If it were to take a new painter one hour to paint a window, how much wall space could they paint in one hour? The goal is for each of your painters to come close to hitting these ‘ideal’ completion times per point based on their level:

  • Apprentice I: Still new, they target 45–60 minutes per point. Focus should be on basic, repeatable tasks.
  • Apprentice II: Building speed, tackling 35–50 minutes per point. They can now handle some slightly more complex work alongside simpler tasks.
  • Apprentice III: Aims for 30–45 minutes per point consistently. Now comfortable with most routine painting jobs.
  • Journeyman I/II: Handles a wide variety of work, targeting 25–40 minutes per point. This skill range represents your solid crew backbone.
  • Journeyman III: Very reliable, works steadily at 20–35 minutes per point. Few jobs will ever throw them off balance.
  • Craftsman I/II: Expect adaptability to challenges within a 20–30 minute point window. Can handle complex work at an efficient pace.
  • Master Craftsman: Also targets 20–30 minutes per point, BUT their main value lies in the ability to confidently and expertly tackle the most intricate, time-consuming tasks.

Important Considerations:

These are rough guides, every painter develops slightly differently. Task complexity will always be a factor! Not all ‘points’ are truly equal in difficulty. Skill leveling isn’t just about raw speed. A steady Journeyman may work within that ‘slot’ forever, while another ambitious painter might rapidly evolve towards Craftsman-level point speed and task expertise.

Planning Sprints With Point Wisdom

Track Past Throughput: How many points does your team actually finish per sprint, on average? This establishes your realistic capacity limit.

Match Tasks to Strengths: Early on, focus on giving apprentices ‘batchable’ tasks for speed gains. Complex jobs are split out based on who does that type of point work fastest and best.

Smart WIP Limits: Knowing how many points are actively ‘in progress’ at any time is crucial. If this regularly balloons beyond what you can complete within a sprint, jobs stall and customers get unhappy!

Note: For a deeper dive into this point calculation method and more complex task breakdown examples, you can order the Craftsman Painter Value-Based Estimating Guide by emailing me at torlando@craftsmanpainter.com.

Scenario: The Impact of Apprentice Growth

Meet Painter Pete. His small crew includes himself (a Craftsman), a skilled Journeyman, and a promising Apprentice named Alex.

Before: Alex’s Early Days

Sprint Bottleneck: While Alex was learning, his 45–60 mins/point on very basic tasks created a slowdown effect. The majority of complex work had to be assigned to the more experienced painters to prevent delays.

Conservative Planning: Pete noticed their historical output for sprints averaged around 500 points, but that felt VERY tight if anything got complicated, leading to stress as deadlines approached.

WIP Worries: Their ‘in progress’ workload consistently teetered near that 500-point level. Any unexpected delays (material issues, sudden client change, etc.) could throw everything into chaos, forcing the more skilled painters into ‘rescue mode’.

After: Alex Levels Up

Skill Shift: With focused mentoring and consistent practice, Alex now operates in the 35–50 minute range per point. He comfortably handles various paint prep and cut-in work, even on projects with some moderate complexity.

Throughput Rise: Without fundamentally changing sprint length, Pete has noticed that the team is more reliably hitting the 550–575 range of point completion. Less time wasted waiting for Alex to finish basic tasks!

WIP Comfort Zone: Since their capacity increased, their WIP buffer feels better. Now, having 500 points active isn’t a frantic rush; it reflects realistic ongoing work within a cycle.

Less “Rescue” Reliance: Higher individual output means Pete and his Journeyman have more bandwidth. Minor project-specific setbacks no longer threaten the whole schedule constantly.

Key Takeaways from Little’s Law

This isn’t about Alex magically working longer hours. It’s smoother overall flow — complex tasks don’t pile up waiting on Pete’s availability.

Pete sees more growth potential: Investing further in Alex’s training might push throughput into the 600-point range within a few months.

Little’s Law helped with decision-making: At one point, Pete considered adding another Apprentice just to ‘have more hands’. Data showed him skill ups had more immediate ROI.

Note: This change opens other planning avenues! Could he justify slightly higher pricing while keeping WIP balanced, given faster finish times? More ‘filler’ jobs between big ones now create less downtime. These options were hidden without Little’s Law insights.

Scenario: The Complexity Spike

Painter Pete’s crew had found a good rhythm. His Apprentice was leveling up, his team was humming along, and throughput was increasing just as expected. Suddenly…

The Client Shift: There’s been a surge in new client inquiries focusing on older homes with intricate trim, custom cabinetry, multiple accent colors — work with many high-point tasks on Pete’s system.

Unexpected Strain: While nobody got slower, sprint throughput starts creeping downwards — jobs in the 550–600-point range now often spill over into additional days, despite no crew changes.

Frustrating Mystery: Cycle times feel sluggish, yet nobody got lazy! Everyone’s still hitting their usual point-per-hour range on most tasks. What’s the culprit here?

Little’s Law Provides Clarity

Complexity != Speed: It’s tempting to blame skill decline with delays, but remember, ‘points per hour’ are based on task type. Highly detailed work always fell on his Journeyman or himself due to skill, so their rate didn’t actually take a hit.

The WIP Warning: While Pete kept an eye on total points to schedule sprints, he wasn’t initially thinking about complexity distribution within them!

Aha! Moment: Looking back, a LOT of high-point projects clustered together. This overburdened the team members capable of those tasks, leading to slower flow despite total hours worked remaining relatively consistent.

Adaptive Strategies: Using Little’s Law Thinking

Lead Time Honesty: Pete cannot magically make everyone faster just on these jobs. He adjusts new client expectations on start dates to reflect longer cycle time reality for this ‘high complexity’ type of work.

Sprint Redistribution: Pete starts consciously balancing sprints. When a 600-point complexity bomb comes in, he fills its ‘counterpart’ sprint cycle with several smaller, less intricate jobs. This balances out the time demand to avoid constant overload.

Targeted Training: Could this shift actually drive an upskill opportunity? Can some of the Apprentice’s simpler prep and trim work be improved so he can be used on moderately complex jobs as a helper initially, freeing up sometime for the more-skilled painters?

Key Point: Little’s Law helped Pete understand the WHY behind the slowdowns when raw manpower hadn’t changed. Adjustments weren’t about fixing ‘people’ but rather how work itself was scheduled to create better workflow again.

Little’s Law & Pricing: Adapting to Complexity

Pete’s crew hit their sweet spot when a decent variety of projects flowed through — some quick wins, some intricate showcases. This sudden high-complexity trend made him confront a hidden consequence:

Hidden Time Cost: While his point structure already accounts for some level of difference, these jobs consistently take longer despite accurate point assessments. He can’t make skilled painters magically produce twice their ‘points’ just for intricate trim work!

Profit Pressure: If project length consistently extends on high-complexity work while prices stay based on old calculations, his projected earnings per sprint dwindle. This eats away at the value of the crew’s skill!

Customer Expectation (Mis)match: Lowering expectations of when projects finish is one thing. Constantly underestimating how complex work impacts revenue isn’t a long-term solution.

Pricing Strategy Informed by Little’s Law

Transparency as Marketing: Perhaps clients don’t realize how ‘point heavy’ intricate jobs truly are. Openly explaining this when providing estimates with examples builds trust and justifies pricing differences.

Tiered Adjustments: A moderate ‘time complexity surcharge’ per project or a point ‘buffer’ applied to work orders with lots of finicky trim is fair as long as it’s explained upfront, not sprung on customers last minute.

The Value Sell: Little’s Law helped Pete see delays weren’t a failing skill-wise. This can be used to promote their experience — “Yes, the price reflects our deep expertise in intricate paint prep; cheaper often means rushed shortcuts, not a job worth doing for these custom-builds”.

Beyond Instant Fixes

Crew Expansion Rethought: If this intricate work trend holds long-term, adding another Apprentice becomes less attractive if the backlog is for highly skill-based tasks. Perhaps finding another mid-level Journeyman (still faster on those details than pure Apprentices) fills the true talent gap for this market.

Niche Potential: Could specializing in these high-detail jobs turn into a profit niche with justified higher pricing? Little’s Law data on what this clientele can realistically expect for timelines may attract those valuing quality finishes above ‘rushed is cheaper’.

Estimating Lead Times: Beyond Rough Guesses

Many painters simply tell clients a vague ballpark (“4–6 weeks out!”), hoping they can squeeze that job in somewhere and meet the timeline. But with data, you can give far better expectations.

Knowing Your WIP: Let’s say, historically, you always carry an inventory of about 400 points of work active in various stages of progress.

Calculating Cycle Time: Your team generally finishes between 300–350 points per sprint (2 weeks). At first, estimate low-end for safety! Say 300 points is your reliable floor for finished work during that cycle.

Example for Clarity

Check The Queue: A new client needs a 200-point job done. Your current in-progress WIP is sitting at 400, its maximum comfortable capacity.

Rough Lead Time Prediction: To clear even some of the backlog, your soonest start (barring cancellations) is likely the beginning of next sprint cycle. It isn’t realistic to magically cram more into the currently overloaded system.

Buffer Based on Cycle: Since most projects will take some duration within that sprint, an extra 1–2 week ‘safety margin’ after theoretical start to finish the actual work is prudent. You don’t want new jobs instantly throwing you back into overload!

Explaining This To Clients

Here’s how you phrase it with both honesty and professionalism, gaining their trust:

“While the actual work itself won’t take overly long, I take my work commitments very seriously. Right now, I wouldn’t want to promise start dates I may not meet on this job type. Based on how my production schedule works, realistically I’m looking at approximately [Calculated Date Range] being the earliest possibility with room to ensure an outstanding finish for you. Would that timeframe fit your needs generally?”

Key Concepts: Honesty Builds Trust

Clients hate uncertainty more than even long waits initially. This method is upfront. Being confident is more attractive than “maybe I can squeeze it in”. This reflects your understanding workload limitations, crucial for pricing and managing customer expectations.

Little’s Law lets you adapt this on the fly! If WIP sits uncharacteristically low, or you have crew skills changes, your predicted wait times dynamically adjust for a realistic approach.

Scenario: When the System Stalls

Imagine this:

WIP Overload: For various reasons (maybe cascading delays due to flu that spread through the team and impacted several jobs), you’re sitting at 550 in-progress points instead of your normal 400. Jobs feel stuck on every little drying wait period!

Throughput Drops: Not because folks are lazy! More time is wasted waiting for things to be ‘ready’ for the next work stage. Cycle times across even normal-size jobs feel sluggish. Throughput has dipped temporarily into the 250–270 point range.

That New Client Calls: They need a 150-point project done soon — typical size, but not crazy complex. The ‘old way’ might have led you to instinctively try to fit it in any way. Little’s Law reveals why this is now dangerous.

Lead Time Reality Under Stress

Backlog Clearing: To even fit another ‘normal’ job in, you first require around 2 sprints at low output just to hit your typical WIP comfort zone for flow to resume.

Realistic Prediction: This client isn’t getting started ‘next month’. Even accounting for some return to normalcy work speed wise, a conservative 6–8 week projection from call date is likely based on current state.

Transparency Wins: “Right now, things are unexpectedly backed up. It wouldn’t be fair to you or my existing clients to promise something I can’t deliver without compromising quality…”

Explanation to Your Crew

Little’s Law helps visualize why ‘try harder’ isn’t the fix here:

“Look at our last few sprints. Even with effort, we barely hit 250 in points — everyone got frustrated waiting on stages they can’t personally push faster.”

“That backlog doesn’t vanish magically. If we cram more in on top of that mountain, every single little snag (weather, client asks for minor change) throws us into chaos further.”

“Here’s the plan: Focus on the current queue with what we can control. New leads get honest but longer timeframes. Less stress long-term is worth that short-term hit of not taking every single piece of work”

Key Insights

Little’s Law isn’t punitive, it’s about healthy boundaries. Crews feel better working ‘at capacity’ than consistently in failure of meeting promised targets due to overload.

This fosters problem-solving. Did an ‘easy project’ unexpectedly drag, highlighting an estimation issue? Did new material have extra cure time the old brand never did? Identifying these matters alongside cycle time changes.

It protects future pricing — being constantly behind means you lack leverage to raise charges as skills improve, clients won’t pay more when delivery is unreliable.

Estimating Lead Times: Leveraging Your Craftsman Painter Tools

In most painting businesses, providing realistic start dates to clients is a mix of educated guessing and hoping for the best. Luckily, the Craftsman Painter system turns your existing workflow into a Little’s Law advantage:

WIP That’s Easy to Visualize: Those Work Tickets aren’t just task reminders! At any given time, those active notes across different job sites represent your true WIP status for calculating realistic capacity limits.

Understanding Cycle Time Bottlenecks: Your Daily Planners offer more than individual point goals. Noticing recurring ‘waiting delays’ across projects highlights whether cycle time slows due to skill gaps or process issues like drying times that need smarter strategies.

Putting It into Practice

A new client’s 250-point job comes in. A glance at the Work Tickets lets you estimate current ‘real’ WIP across various projects.

Planner data over recent weeks indicates your team reliably hits that 300-ish point range during your sprints without everyone feeling burnt out.

This lets you be honest with clients: If current WIP sits high, those start dates become weeks out while maintaining realistic workload for your team. No need for fancy spreadsheets as your calendar is doing the hard work. Just schedule each job according to the points and the points capacity of the crew you’re assigning to the job.

Communicating Value to Clients

This sets you apart from painters just giving vague promises. Little’s Law, combined with your system, lets you confidently explain:

“My commitment to quality means carefully managing my workload. This allows me to provide realistic timelines and avoid compromising standards by taking on too much.”

“I use workload tracking to provide my clients with accurate and reliable timelines, This approach avoids vague commitments like ‘hopefully next month’.”

Boosting Crew Understanding with Little’s Law

This isn’t just about you as the boss. Concepts like WIP and cycle time might feel vague, but the Craftsman Painter Work Ticket system and Daily Planner put them directly into crew member hands:

  • The Impact of Points: Those daily points add up! Seeing sprint totals versus their personal output connects ‘busy’ to actual WIP load in a relatable format. Especially for younger crew members who have a side passion for things like gaming or pickup basketball. Our ‘put points on the board’ mentality gamifies work in a way that’s gratifying and competitive.
  • “Stuck Time” Gets Noticed: Detailed timings make those 30 minutes of active work followed by ‘waiting on coat to dry’ stand out. Motivates crews to find solutions beyond pure brush speed for overall throughput increase.
  • Skill Balance Matters: If Work Tickets pile up at certain stages due to individual strengths, it opens proactive training discussions without feeling ‘punitive’ about speed. Your data lets you target development to improve overall flow. Remember that for each skilled worker, their production output by point should have a consistent time to it. If they are producing individual points at radically different speeds, that is an indicator that either they are working on a work ticket with a level of complexity that out matches their skill level. This requires more training or reassignment, or the estimate needs improvement.
  • Unclog Blockers: This sets up a discussion of the impact of blockers and bottlenecks. Close monitoring of the Work Tickets and their impact on flow is the key to enhancing productivity. Getting crew buy-in on close adherence to the Work Ticket system is going to be critical. I’d rather have a crew leader who can wrap their mind around this concept than one who is a Master Craftsman. That person is going to grasp the vision of what true flow can look like.

Identifying Bottlenecks: Where Your System Stalls

Understanding bottlenecks is your key to unlocking better paint business operations. Think of them like a clog in your workflow, slowing the entire process down. Here’s why this matters:

  1. Throughput vs. Effort: Working harder often isn’t the answer! (What?!?) A bottleneck means even the most skilled crew gets stuck waiting for something; effort does not translate into finished projects at the desired pace.
  2. Frustration to Motivation: Bottlenecks lead to that ‘busy but no progress’ feeling for your crew. Identifying them shifts focus from blame towards system fixes: better for everyone’s morale!
  3. Client Experience Upgrade: When projects lag, customers don’t see the reasons, just delays. Little’s Law helps pinpoint whether scheduling mistakes or even product choices are secretly extending job durations! Better control means happier clients.
  4. Lost Profit Potential: Overloaded WIP limits project intake. Removing bottlenecks could mean handling significantly more work without extra staffing (as long as painter skill meets the increased demand).

Spotting Bottlenecks Using Little’s Law

Your existing records hold the clues:

WIP Outpacing Throughput: Is that ‘active points’ tally consistently outstripping how much is truly getting finished per sprint? This is your red flag that workflow stutters somewhere. Don’t just work ‘overtime’ if the fundamental issue remains!

Drying Wait = Wasted Time: Dry times are part of the job, but excessive delays here signal bottlenecks. Could faster-dry material (if cost-effective) boost work completion, letting more coats happen during the same day? Could strategically planning tasks that require 24 hr dry time be done ahead of queue? Could things requiring an hour or two be completed right before lunch or heading home?

The Task Breakdown: Those detailed Daily Planners don’t just track points! A sudden slowdown on ‘routine’ tasks means one needs attention. Is complexity underestimated? Or could assigning it to someone stronger on that element make overall crew throughput increase?

Beyond The Obvious: It isn’t just about paint! Client change requests, weather disruptions, illness, supplier backorders also tank smooth progress if the ‘aftershock’ of WIP isn’t accounted for when planning future sprints.

Key To Action

Little’s Law doesn’t fix problems by itself. This data is your diagnostic tool:

Focus, Not Fury: Isolate what causes the slowdown the most — is it one recurring job type, one team member’s workload, etc. That narrows down where solutions will have the most impact.

Small Changes, Big Gains: Removing a bottleneck might be as simple as identifying when a painter gets ‘stuck’ on the prep stage due to insufficient tools that others are using. Not a big expense, but can yield noticeable throughput wins if it impacts many projects!

Honesty With Clients: A ‘complicated trim’ job now has extra delays due to rain… being transparent using Little’s Law thinking about how this cascades builds long-term trust, even if short-term adjustments must be made.

Identifying Bottlenecks and Targeted Solutions

Little’s Law makes those ‘why is everything slow lately’ moments actionable. Here are common indoor paint workflow bottlenecks along with potential strategies to combat them:

The Drying Time Drag

Symptom: Project stalls mid-cycle waiting for patches and caulking to dry, walls to second coat, coats on trim to cure, etc. Everyone looks ‘busy’ but WIP isn’t going down at its ideal pace.

Mitigation Strategies:

Product Choice: Are faster-dry options possible, if cost/client expectations allow? Balancing that gain against slight price or process adjustments is data-driven, not guesswork.

Smart Sequencing: Could smaller rooms be prioritized for full day ‘paint and done’? While large zones dry, less ‘wait prone’ prep happens elsewhere. Batch processes where the color is the same across multiple rooms to avoid switching costs.

Ventilation Investment: Fans, dehumidifiers (when air conditions allow) can be worth their cost if they remove HOURS across multi-coat drying stages.

Process Order Inefficiency

Symptom: Jobs feel chaotic. “We already painted this…” arises from not communicating or fixing/add-on work that muddies your schedule. This adds extra steps to WIP!

Mitigation Strategies:

Workflow Templates: Preset room order (experiment with different orders to validate the fastest processing time) minimizes decision fatigue onsite, especially with larger crews. Less chance of rework!

Clear Client Communication: Upfront details of what rooms require ‘furniture clear’ versus ‘light shuffle’ lets prep stages flow in the right order if clients meet their end.

Prep as Skill Emphasis: If prep causes cycle time spikes, it’s NOT ‘unskilled’ work. This may become a designated role on larger jobs for someone highly efficient at setup masking tasks to support smoother paint stages later.

Skills Gap Slowdowns

Symptom: Specific task types constantly end up behind. It may not be about speed, but frequent rework needs on one element (especially complex repairs!) throws the entire flow off.

Mitigation Strategies:

Honesty Over Ego: Is that Apprentice just slow, or thrown at tasks currently beyond them? Targeted mentoring now boosts later speed more than vague frustration of everyone trying to fill in.

Delegation Upwards: A job with many finicky, time-consuming details may warrant your Craftsman taking the lead; Apprentice focuses on simpler prep/fill/mask supporting them for overall speed rather than trying to rush their personal progress.

‘Batch’ Tasks: On lower-complexity jobs, clustering all baseboard bursts may improve Apprentice proficiency faster than constant switching between complex/easy tasks that slows them down on everything. Balance this with spending too much time doing one task, which can end up dragging due to monotony.

Beyond ‘Obvious’ Painting Bottlenecks

Little’s Law’s focus on WIP/throughput highlights things most painters don’t even track:

Client Hesitation: Are jobs stalling while waiting for color choice, that furniture move, etc.? Building ‘decision buffers’ into client timelines mitigates their indecision, impacting your profits.

Disorganization’s True Cost: Constant tool hunts and store runs eat productive time. Investing in smart storage (even on budget!) frees up hours better spent actually painting.

Personal Productivity Habits: Your crew’s phone ‘breaks’, the ‘early pack up’ routine before the job’s truly done…these become quantifiable in lost points per week impacting WIP, not just ‘bad attitude’ issues.

Important: Little’s Law is the flashlight pointing out issues. Solutions may take trial and error! This makes tracking post-change throughput even more essential for continuous improvement.

Planning Sprints Strategically: From Theory to Action

Little’s Law provides a framework for realistic sprint planning. Here’s how to apply it alongside your Paint or Design Rep:

Calculate Your ‘Ideal’ Capacity

Gather Data: Calculate total working hours per painter within your typical sprint (e.g., two weeks).

Consult Your Rep: Discuss project performance to get “points per hour” averages for each individual member. Add the average points per hour of each crew member to determine the total points per hour of the crew.

Estimate Individual Output: Multiply each painter’s hours by their average output (e.g., apprentice: 1.25 points/hr * 80 hrs = 100 points). Add these values for your theoretical crew maximum.

Reality Check: Actuals vs. Ideal

Analyze Past Performance: Review historical records to determine what your team actually completed in terms of points, even during successful sprints.

Start Conservatively: If your ‘ideal’ is 500 points, but your team typically achieves 420, begin your sprint planning closer to the lower number to avoid overpromising.

Investigate Gaps: Identify the causes of discrepancies. Are delays due to unforeseen issues (e.g., material shortages) or consistent bottlenecks (e.g., a specific job type that exposes team weaknesses)?

The Results

Ideal Above Actual: This highlights areas for improvement — inefficient task distribution, skill gaps, or inaccurate pricing.

Ideal Matches Actual: You’ve found the sweet spot! With this knowledge, you can accurately manage work-in-progress, lead times, and expectations.

Ideal Below Actual: This is a red flag! You’re likely overloading your team. Reassess job estimates or pinpoint work process slowdowns hindering your crew’s full potential.

Key Points

  • Sprint planning done right should be a collaborative effort with your paint rep (the person who sold the job) and crew leader (the person responsible for producing the job).
  • Starting conservatively prevents burnout and unrealistic expectations.
  • Use data from past sprints to calibrate your ‘ideal’ capacity over time.

Scenario: Sarah and Pete Plan a Sprint

Sarah (Owner): “Pete, let’s nail down this sprint planning. Remember, we want to be realistic about capacity, especially since you’re training Tom.”

Pete (Crew Leader): “Right. Lately, with a mix of training and my own jobs, I’m more at about 2.5 points per hour. Tom’s improving, but averages in the 1.25–1.5 points per hour range. Melissa, though, she’s solid at 2 points per hour.”

Sarah: “Those numbers make more sense. Let’s do some math for a typical 8-hour workday. You’re closer to 20 points a day, factoring in that training time. Tom averages around 10–12, and Melissa hits 16.”

Pete: “Okay, across two full workweeks in a sprint, at the low end, that’s about 200 points from me, 100 from Tom, and 160 from Melissa. That total, roughly 460 points, feels way more accurate.”

Sarah: “Agreed. But remember, with our point system, those hours don’t always neatly turn into points. Let’s aim for 400 points this sprint. Let’s pick jobs that balance the load but let Tom learn on the simpler things too.”

Pete: “Sounds good. I’m even wondering if there are small bonuses for hitting that 400? It helps everyone stay motivated, knowing some extra cash is attainable.”

Key Takeaways

Accurate Point Estimates: Sarah and Pete adjust their projections based on a more realistic ‘points per hour’ breakdown.

Training Impact: They acknowledge that Pete’s training responsibilities reduce his personal point output.

Conservative Planning: Despite potentially being able to hit 460 points, they set a lower 400-point target, leaving room for unexpected delays and focusing on Tom’s growth.

Incentives: Pete explores the idea of bonuses, promoting accountability and potentially increasing the team’s output.

Scenario: Sarah and Pete Plan the Next Sprint

Sarah (Owner): “Okay Pete, this next sprint, I want us to select larger projects to leverage the whole team. Remember, Tom still needs supervision, and Melissa works well with those separate smaller tickets.”

Pete (Crew Leader): “Right, so that makes things a bit more challenging with our 400-point goal. Based on last week, how many hours did supervising Tom realistically take away from my full productivity?”

Sarah: “That’s a good point. Let’s look. From these numbers, it cuts your daily point output by about a third. Does that feel right?”

Pete: “Yeah, especially early in the sprint when he’s got more questions and I have to do more running around. That puts me closer to 12–15 points a day if we’re together full-time.”

Sarah: “Okay, in that case, let’s see if we have two medium-sized houses — around 75 points each. That accounts for most of your time. Tom can help, gaining experience but at his slower pace.”

Pete: “And for Melissa, let’s find trim/detail jobs she can lead on at those two client locations. Maybe that accounts for another 50 points between them, while also improving those skills.”

Sarah: “This would leave us at about 250 points. If a smaller repainting job comes up around the 50-point mark, we could easily take it on.”

Pete: “That buffer might be wise. And hey, if all three of us exceed expectations on those main houses, is there still that bonus possibility to push us harder?”

Key Takeaways

  • Supervision Impact: They explicitly calculate how Tom’s training cuts into Pete’s individual output.
  • Combined Effort: The focus is on jobs requiring their teamwork to maximize the potential 400 points.
  • Melissa’s Autonomy: Sarah identifies separate ‘tickets’ for Melissa, showcasing her independent capabilities during the sprint.
  • Buffer Zone: Planning slightly under the 400 points again demonstrates awareness of learning curves and potential unforeseen issues.
  • Warning: For the sake of realistic numbers, production may use this as an opportunity to reduce the pressure of producing. Remember the bottom line. You have to make money. If producing fewer points means that Pete costs more money than he’s producing, then you’ll have to moderate the number of points Pete is expected to produce and help him not lose sight of the goal to make money. No money, no bonus.

What the Research Suggests About Cash Incentives:

Short-Term Gains, Long-Term Risks: Simple cash bonuses tied to output can provide immediate performance boosts. However, studies show this effect often tapers off. Regression to the mean is common, especially if those early gains were unsustainable.

Focus Shift: Extrinsic motivation (money) can overshadow intrinsic motivators (pride in work, learning). Employees may sacrifice quality or long-term improvements for faster output to hit incentive targets.

Unfairness & Demotivation: When goals are unrealistic or rewards vary depending on the job, it can lead to resentment and lower morale among those feeling it’s unattainable or not worth the effort.

The Bigger Picture: Research in behavioral economics points out that while money matters, non-monetary factors typically have a more enduring impact on motivation: growth opportunities, recognition, positive team atmosphere, sense of purpose.

Making Cash Incentives Work (If you go that route):

Realistic Goals: Ensure sprint targets are genuinely achievable while considering the whole crew’s capacity and learning curves.

Emphasis on Mastery: Frame the bonus as a reward for both hitting the target AND maintaining quality standards.

Team-Based, Not Individual: This fosters cooperation over competition, especially important to Pete and Tom’s dynamic.

Small But Frequent: Modest but consistent rewards help create a feeling of progress without making cash flow unpredictable.

Part of the package: Tie incentives to opportunities for skill development and more engaging work to foster long-term growth.

Know Your Break Even: The point system aids in determining our break-even point effectively. By mathematically linking their base pay to a specific dollar amount per point, we can calculate the difference between the revenue they generate per hour and the cost they incur for the company. Understanding the break-even point helps in determining how much of the profits can be allocated as productivity bonuses.

Alternatives to Consider with Sarah and Pete

Skill Development Incentives: Rewarding Tom for gains in points per hour or new skills mastered adds a learning focus.

Quality Measures: Bonuses attached to positive customer feedback or minimal rework promote doing the job right the first time.

Growth-Based Perks: If the target is hit and capacity increases, unlock things like better equipment or choice of projects.

Open Communication: Discuss the pros and cons of incentives honestly with the crew. Get their input to find what truly motivates them.

Important Note: It’s about finding solutions that fit the company, the team, and the nature of the work. What works for one painting company might not suit another!

Profit and Efficiency: The Connection

Time is Money: The faster your crew consistently operates, the more jobs (and profit) you can potentially take on in a given period.

Competitive Advantage: Efficiency makes your pricing more competitive. You can offer similar rates as others while having a better profit margin, or be slightly higher, knowing customers perceive higher value due to the job getting done sooner and with less disruption to their lives.

Value Justification: Price increases paired with a track record of fast, good work make clients less likely to push for discounts.

Caveat: Efficiency shouldn’t become an obsession at the cost of quality, safety, or employee burnout. These will erode profits over time.

Questions for Analyzing Your Efficiency

Tracking Methods: How do you currently measure speed and performance? Per-point timelines, completion checklists, project management software?

Past vs. Present: Do you have historical data to compare against? This lets you measure the impact of process changes or training.

Bottlenecks: Where do most slowdowns happen? Is it material delays, specific job types, individual weaknesses, or communication breakdowns?

Investment for the Future: Could equipment upgrades or more training yield significant long-term gains, justifying some price adjustment now?

Scenario: Sarah Reassesses Pricing

Sarah digs into her records, comparing past projects with a recent upswing in team efficiency due to:

New Roller Technique: A training session made everyone 10% faster on walls.

Process Tweak: Standardizing the job setup phase shaves off hours overall.

Melissa’s Growth: With more responsibility, she frees up Pete’s time.

Sarah realizes they can take on slightly larger jobs in the same timeframe. After factoring in material costs, she could:

  • Option 1: Keep prices as-is, enjoying a boost to her bottom line, and increased bookings due to speedier turnarounds.
  • Option 2: Raise prices by a modest 5%, using the “faster & equally reliable” message for client-facing material.

Little’s Law can aid in making this decision, but ultimately, the “best” option depends on several factors beyond what the law tells us. Here’s why:

What Little’s Law Tells Us

Little’s Law (Cycle Time = Work-in-Progress / Throughput) primarily helps to:

  • Measure average time a job spends in your system (from contract to completion).
  • Diagnose process problems when there’s a mismatch between workload and completion rate.
  • Predict how changes will affect your workflow — If you increase workload, will cycle time stay stable? This impacts job scheduling and client expectations.

How Little’s Law Informs Sarah’s Choice

Knowing Sarah’s crew is faster allows her to use Little’s Law:

If they keep their current workload but complete it faster, cycle time shortens — great for taking on new contracts without overpromising deadlines.

If Sarah wants to grow her work-in-progress (take on more), she now has the throughput to support it while maintaining manageable cycle times.

This is where factors beyond Little’s Law come into play for Sarah:

Market: How price-sensitive are her clients? Is speed a deciding factor? Does her competition highlight these things?

Reputation: Is she focused on building on speed, quality, or a mix? This informs a pricing message if she goes that route.

Profit Goals: Does Sarah prioritize a significant immediate boost to the bottom line, or long-term strategic growth made possible by reinvesting increased profit into training and equipment?

The ‘Best’ Option in Light of These:

  • Option 1 (Keep Prices, Maximize Speed): Good for a saturated market, emphasizes value if Sarah’s current rates are already competitive. Could create cash flow for faster equipment purchases that further increase efficiency.
  • Option 2 (Modest Price Rise): Best if clients value both quality and urgency and perceive Sarah as offering something others don’t. Requires solid evidence supporting her team’s increased efficiency, as not every client will see the additional value without an explanation.

Key Strategies Inspired by Little’s Law

1.Work in Parallel: Stagger work areas or entire projects so drying time in one area doesn’t cause a total work stoppage.

  • Throughput Focus: By having work available across multiple areas or jobs, you don’t lose throughput while waiting for one area to become ‘available’ again.
  • Cycle Time Reduction: Instead of a job’s time equaling drying time + work time, your cycle time decreases because different sections move ahead simultaneously.
  • Bottleneck Buster: Drying is now less of a bottleneck since your crew has alternative actions in progress to maintain your desired pace.

2. Task Specialization: Match work complexity to painter skill, optimizing overall pace.

  • Maximizing Work-in-Progress (the right type): This isn’t about overloading with difficult jobs, but ensuring easy tasks go to less experienced painters while seasoned ones handle the complex parts.
  • Optimizing Flow Rate: This directly targets a potential cause of decreased flow rate — slowdowns on tasks beyond current skill levels. It keeps everything as efficient as possible.
  • Little’s Law Reminder: With more ‘right’ work-in-progress, and a faster average flow rate, Sarah can be confident cycle times remain predictable for scheduling.

3. Fast-Drying Products: Reduce forced ‘wait’ phases to shorten cycle time.

  • Self-evident Cycle Time Decrease: Quite possibly the most direct action for shortening the job completion time, especially when clients favor companies that can hit tight deadlines.
  • Investment vs. Savings: Little’s Law helps Sarah analyze if these products pay for themselves — higher material cost, but more jobs within a defined period means potentially higher profit than using cheaper options with greater open times.
  • Caveat: This alone likely won’t fix underlying workflow problems! If those still exist, this just moves the bottleneck elsewhere.

4. Process Documentation: Create standardized workflow visuals to identify bottlenecks and ensure consistency

  • Bottleneck Hunter: Visualized processes reveal unexpected holdups — is it lack of tools at steps, unclear job orders, or a task taking most crews unusually long?
  • Supports Flow Rate Consistency: This ties directly to throughput predictability (Little’s Law!), which is vital when promising deadlines. Knowing your range prevents overpromising.
  • Onboarding Assistant: With this systematized, new employees learn how everything SHOULD flow faster, reducing delays caused by learning on the fly.

Additional Notes

Data Matters: Tracking time (even roughly) per-task across project types reveals what optimization gives the biggest reward. Is it product, personnel, or process-focused first?

Little’s Law Is Flexible: If client requests grow, Sarah uses the law to predict if she has the work hours for expansion while keeping lead times stable, OR decides to lengthen her waitlist slightly while keeping cycle times in the current customer’s favor. This builds reputation in It’s way too!

Conclusion: Little’s Law in Action — Beyond Theory to Success

Little’s Law may seem like a simple formula, but in running a paint business, it offers a framework for making smart, data-informed decisions. This isn’t just about numbers; it impacts:

Efficient Sprints: Don’t get caught in a cycle of overpromising and underdelivering. Little’s Law helps you create realistic sprints based on capacity, avoiding burnout and client disappointment.

Skill-Driven Growth: Little’s Law reveals where skill gaps or mismatched job assignments create bottlenecks. This fosters continuous improvement for your team, leading to faster, more consistent results.

Confident Pricing: Whether raising prices moderately, holding steady to maximize volume, or investing in speed-boosting tools — Little’s Law informs how efficiency gains translate into profit potential.

Satisfied Clients: Shorter cycle times (done right!) delight customers with timely job completion. Building a “fast and reliable” reputation strengthens your standing in the market.

Empowered Planning: No more guesswork! Little’s Law illuminates how potential changes — in crew size, products, or processes — impact your lead times and workload capacity.

Remember:

Little’s Law is a starting point, not a magic bullet. Your industry knowledge and customer understanding are still vital for refining decisions.

Tracking is Key. Simple methods for capturing “point time” averages, job completion times, and client feedback make insights easier, so you can continuously update your “ideal” sprint calculations.

It’s a Journey. Don’t expect perfection overnight. Experiment with small changes, measure your results, and adjust. That’s where progress truly happens.

With Little’s Law as your guide, you’ll gain increasing mastery over workflow, team development, and ultimately, achieve the business growth you envision. Let those faster turnovers and repeat happy customers be a testament to your success!

Simple tracking processes to help you put Little’s Law to work. Our goals are:

  • Ease of Implementation: Nothing overcomplicated, especially as the crew adjusts.
  • Focus: We’ll target those data points essential for Little’s Law calculations.
  • Scalable: This can grow more sophisticated as Sarah gains insights.

Here are a few options you could try:

Option 1: The Daily Point Log

What: A simple notebook or spreadsheet where each painter records:

  • Job Name/Number (unique identifier)
  • Points completed that day according to their system
  • Hours worked (even roughly — 4, 6, etc.)
  • Notes (optional for bottlenecks like “waited 1 hour for material”)

How it Helps:

  • Tracks individual output to refine sprint expectations.
  • Reveals job types that typically take longer, impacting work scheduling.
  • Notes, start identifying hidden issues that impact cycle time.

Option 2: Project Timeline Board

What: Visual board in the work area, divided into simple stages:

  • To-Do
  • In Progress
  • Drying/Waiting
  • Done

Jobs get represented as simple cards moving across the board.

How it Helps:

  • Identifies bottlenecks at a glance — is the ‘waiting’ column always full?
  • Promotes faster communication when holdups happen.
  • Gives instant snapshot of the overall work load (Little’s Law’s ‘WIP’).

Option 3: Client Feedback Form

What: Simple form on jobs (even digital if clients are into that) asking:

  • Date contract signed
  • Date work completed
  • Was the timeline as promised? (yes/no/somewhat)
  • Open comment area for issues beyond just on-time delivery

How it Helps:

  • Tracks cycle time directly from the client perspective.
  • Reveals if perception matches internal understanding.
  • Early warning system for client satisfaction problems you might have missed.

Important Considerations

Start Small: Maybe it’s JUST the project board first, see how the crew engages.

Tie Incentives to Participation: If logging points seems onerous, those ‘extras’ you can offer help initially. Make it part of the job routine, not an annoying extra step.

Analyze Together: Have quick daily check-ins with the crew about what the tracked data is SHOWING them. This builds shared understanding of the purpose beyond your spreadsheets.

Take Your Skills to the Next Level: The Craftsman Painter Collective

Throughout this guide, we’ve focused on improving your speed, efficiency, and commitment to exceptional work. But what if you want to be part of something where those passions are shared and celebrated?

The Craftsman Painter Collective is a nationwide network of painters who, like you, put quality at the forefront. Here’s what you gain:

  • Community: Connect with peers, share expertise, and find mentorship to constantly up your game.
  • Brand Power: Build your reputation under a trusted banner recognized for high-end work.
  • Business Support: Benefit from shared resources, lead generation, and tools to smooth out the operations side of things so you focus on what you love — painting.

Is the Collective right for you? Visit craftsmanpainter.com/collective to learn more and become part of the movement elevating the painting trade.

--

--